About us

LLC «PPRK-Service» was established in 2007. For the period of its existence, the company «PPRK-Service» has taken a firm position in the field of development of production projects not only in St. Petersburg, but also in many cities of Russia.

What's the secret?

Such a rapid progress is due to the fact that the company has been working for real professionals since its formation, both people with experience in this field for more than 30 years, and young, energetic, purposeful specialists with a new, modern approach to work. This allows, at the current pace construction meet the requirements of the customer, both in quality and in terms of the development of production projects (PPR).

Thanks to our experience ..

If necessary, we agree on the development of the projects for the production of work (PPR) developed by us with all authorized organizations.
Thanks to the accumulated experience in the development of the crane production project (PPRC), we have knowledge of industrial safety requirements, and take them into account at the development stage of the PPRC, which allows us to receive positive conclusions from the industrial safety expertise in the shortest possible time.

Professionals !!

The indicator of our successful work is the projects we have developed for the production of works (PPR, PPRK) in various areas of construction. We have experience working with civil construction organizations (excavation, foundation, construction of building frames, installation of roofs, finishing of premises, installation of engineering systems, equipment, etc.). And also with specialized organizations, which conduct their work in the construction of highways, laying oil pipelines and gas pipelines, installing communication lines, etc.

In civil engineering, our company develops the following types of production projects:

one-688064_960_720.png

construction of the zero cycle — the construction of excavations, prefabricated, monolithic and pile foundations, the erection of underground structures (parking lots, parking lots, cellars)

two-688063_640.png

construction of the above-ground part of the building — installation of columns and ceilings, installation of metal structures, installation and installation of wall fences, construction of monolithic reinforced concrete structures

three-688061_960_720.png

installation of engineering systems — heating, ventilation, sewerage, water supply, air conditioning

four-688062_960_720.png

Finishing work

five-688059_640.png

landscaping

six-688060_960_720.png

development of projects for the production of cranes (PPRC)

In industrial construction, our company develops the following types of production projects:

one-688064_960_720.png

construction of the zero cycle — the construction of foundation pits, prefabricated, monolithic and pile foundations (pile and bored piles, «wall in the ground»), foundations for equipment, underground structures

two-688063_640.png

construction of the above-ground part of the structures — installation of columns and ceilings, installation of metal structures, installation and installation of wall fences, installation of monolithic reinforced concrete structures, installation and dismantling of gassing shafts, installation of overpasses and galleries

three-688061_960_720.png

installation of engineering systems — heating, ventilation, sewerage, water supply, air conditioning, fuel lines

four-688062_960_720.png

installation of equipment

five-688059_640.png

landscaping, installation of helipads

six-688060_960_720.png

development of projects for the production of cranes (PPRC)

Work operation plans and method statements for crane operation at installation and transportation of the equipment. At erection, reconstruction, modernization of the industrial enterprises and constructions

one-688064_960_720.png

development of a transport scheme for the delivery of equipment

two-688063_640.png

loading, unloading of large-capacity, large-scale equipment from the barge, trailer, trawl, railway platform with the use of the following load-lifting mechanisms — automobile, caterpillar, gantry, bridge, gantry cranes up to 750 tons, hoisting portal systems (PPS) up to 2000 tons

three-688061_960_720.png

installation of technological equipment with the use of the following load-lifting mechanisms — automobile, tracked, bridge, up to 750 tons, lifting portal systems (gps) up to 2000 tons